Work Profile Report [62W13]

Balance work of widening to 2-lane with geometric improvement from km 60.00 to 64.825(Actual chainage as per site km 59.700 to 64.525) on NH-507 in the state of Uttarakhandunder NH(O) for the year 2023-24 under EPC mode.
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : RO/UK/2023-24/Balancework /NH-507 (Computer No. 235160) -job no -RO/UK/AP/NH-507/2024-25/684

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

3649.52

Resanction Cost :

3649.52

Tentative Cost :

3649.52

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

3,649.52

Demand :

1,140.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

none

Sanction on : 10 months 1 week ago

13 Jun 2024

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

35 %

Tentative Completion date on : 1 year 2 weeks from now

15 May 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4.825
4.825
4.825
-

Remark

view all

-- as on 13-Feb-2025

Rating : 134

No Forest Case in The Work

No Hindrance / Bottleneck