Work Profile Report [62W13]

Balance work of widening to 2-lane with geometric improvement from km 60.00 to 64.825(Actual chainage as per site km 59.700 to 64.525) on NH-507 in the state of Uttarakhandunder NH(O) for the year 2023-24 under EPC mode.
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

प्रशासनिक अनुमोदन विवरण : RO/UK/2023-24/Balancework /NH-507 (Computer No. 235160) -job no -RO/UK/AP/NH-507/2024-25/684

प्राविधिक स्वीकृत लागत (लाख) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

स्वीकृत Cost :

3649.52

पुनः रीक्षित Cost :

3649.52

Tentative Cost :

3649.52

Exp. अंतिम वित्तीय वर्ष :

0.00

For CFY 2025-2026

अवशेष :

3,649.52

Demand :

1,140.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

none

स्वीकृत on : 10 महीने 2 सप्ताह पहले

13 Jun 2024

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

35 %

कार्य की अनुमानित समाप्ति तारीख on : एक वर्ष 2 सप्ताह में

15 May 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

मद
स्वीकृत
पुनः रीक्षित
अंतिम वित्तीय वर्ष
For cfy 2025-2026
अवशेष
लक्ष्य
प्राप्ति
Road [Km]
4.825
4.825
4.825
-

टिप्पणी

view all

-- as on 13-Feb-2025

Rating : 132

No Forest Case in The Work

Hindrance / Bottleneck : बाधा रहित

Assets :

Work not linked with IM

Bridges on The Basis of AI: