Work Profile Report [9W425]

मानखण्ड मन्दिर माला मिशन के अन्तर्गत श्री कैंची धाम मे सौन्दर्यीकरण एवं प्रकाशीकरण का कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

  • Samples

Administrative Approval Detail : E-File No 67287 dt. 13-03-2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

2815.68

Resanction Cost :

4081.38

Tentative Cost :

2815.68

Saving

1265.70

Exp. Upto Last Fy :

267.38

For CFY 2025-2026

Remaining :

3,814.00

Demand :

2,195.00

Allotment :

154.15

Exp in CFY :

154.15

Total Up to Date Exp :

421.53

Construction Started

Sanction on : 1 year 2 months ago

13 Mar 2024

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

10 %

Tentative Completion date on : 1 year 1 day from now

11 Jun 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1
1
0 (0.000m)
1
0 (0.000m)
0 (0.000m)
Jobs
1
1
0
1
0
0

Remark

view all

कार पार्किग हेतु स्थल विकास का कार्य प्रगति पर। -- as on 29-Jan-2025

Rating : 29

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand