Work Profile Report [9W15]

कैंची हरतपा मोटर मार्ग के किमी0 4 से तितोली तक मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

  • alerts
  • Documents

    Samples

Administrative Approval Detail : 2555/।।।(2)/ 06-41(प्रा0आ0)/ 06 दिं0 26.09.2006

TS Amount (lakhs) : 228.57 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

104.40

Resanction Cost :

228.57

Tentative Cost :

228.57

Exp. Upto Last Fy :

227.16

For CFY 2025-2026

Remaining :

1.41

Demand :

2.89

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

227.16

In Maintenance After Completion

Sanction on : 18 years 6 months ago

26 Sep 2006

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 3 weeks ago

31 Mar 2024

Actual Completion Date : 1 year 3 weeks ago

31 Mar 2024

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
3.9
3.9
-

Remark

view all

मार्ग का निर्माण कार्य पूर्ण। -- as on 03-Jul-2024

Rating : 100

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: