Work Profile Report [8W21]

एस॰सी॰पी॰ के अन्तर्गत नन्दप्रयाग -देवखाल मोटर मार्ग के किमी॰ 3 से दादर तक मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 827/।।।-2/06-76 (प्रा॰आ॰)/05 दि॰ 28.03.06

TS Amount (lakhs) : 162.48 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

162.48

Resanction Cost :

162.48

Tentative Cost :

162.48

Exp. Upto Last Fy :

62.58

For CFY 2025-2026

Remaining :

99.90

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

62.58

Construction Started

Sanction on : 19 years 3 weeks ago

28 Mar 2006

Physical Progress:

At start of FY 2025-2026 :

70 %

Up to Date :

70 %

Tentative Completion date on : 3 weeks 3 days ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
6
6
-

Remark

view all

प्रस्ताव सं॰ एफपी/यूके/रोड/10434/2015
वर्तमान में मार्ग के स्वीकृत समरेखण के किमी0 1 के पश्चात् भू-स्खलन होने के कारण भूर्गवेत्ता द्वारा उक्त समरेखण को अपनी आख्या दिनांक 25.01.2023 से अनुपयुक्त बताया है व एक नया समरेखण चयनित कर अग्रिम कार्यवाही करने का सुझााव दिया है। नये समरेखण पर सर्वे कार्य पूर्ण कर लिया गया है परन्तु ग्रामीणों द्वारा आतिथि तक अनापत्ति प्रमाण पत्र उपलब्ध नही कराया गया है। अतः ग्रामीणों से शीघ्र अनापत्ति प्रमाण पत्र प्राप्त अग्रिम कार्यवाही की जायेगी।
-- as on 25-Mar-2025

Rating : 70

Forest Case Pending At : 11: AIP Division

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: