Work Profile Report [8W190]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 818/।।।(2)/14-48 (प्रा0आ0)/2013 दि॰ 08.02.2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
141.84
Resanction Cost :
2.26
Tentative Cost :
2.26
Exp. Upto Last Fy :
2.26
For CFY 2025-2026
Remaining :
0.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.26
Survey work done
Sanction on : 11 years 10 months ago
08 Feb 2014
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान मे यह सड़क पीएमजीएसवाई में फेस 4 में सम्मलित है। -- as on 08-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: