Administrative Approval Detail : ई पत्रावली संख्या 33725 दिनांक 27/10/2023
TS Amount (lakhs) : 149.59 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
149.59
Resanction Cost :
149.59
Tentative Cost :
149.59
Exp. Upto Last Fy :
74.81
For CFY 2025-2026
Remaining :
74.78
Demand :
74.78
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
74.81
Construction Started
Sanction on : 1 year 5 months ago
27 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 4 weeks 1 day ago
26 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 05-Apr-2024