Work Profile Report [71W871]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लोक निर्माण विभाग देहरादून के पत्रांक-895/07 याता- पी0एम0 जी0एस0वाई0-नि0 ।।। दिनांक 16/5/2023
TS Amount (lakhs) : 416.02 Lacs
Budget Financial Head : अनुरक्षण ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
416.02
Resanction Cost :
416.02
Tentative Cost :
416.02
Exp. Upto Last Fy :
340.68
For CFY 2025-2026
Remaining :
75.34
Demand :
75.35
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
340.68
Work completed
Sanction on : 1 year 11 months ago
16 May 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 weeks 2 days ago
25 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: