Work Profile Report [71W839]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter 44547 Dated 27/02/2023
TS Amount (lakhs) : 118.41 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
118.41
Resanction Cost :
118.41
Tentative Cost :
118.41
Exp. Upto Last Fy :
114.89
For CFY 2025-2026
Remaining :
3.52
Demand :
3.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
114.89
Work completed
Sanction on : 2 years 1 month ago
27 Feb 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand