Work Profile Report [71W746]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6128/।।। (2)/ 21-36 (एम0एल0ए0)/ 2017टी0सी0 दिनांक 21/12/2021
TS Amount (lakhs) : 59.49 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
59.49
Resanction Cost :
59.49
Tentative Cost :
59.49
Exp. Upto Last Fy :
48.28
For CFY 2025-2026
Remaining :
11.21
Demand :
11.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
48.28
Work completed
Sanction on : 3 years 4 months ago
21 Dec 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 4 months ago
30 Nov 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 02-Dec-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand