Work Profile Report [71W737]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0-5709/।।। (2)/ 21-40 (एम0एल0ए0)/ 2017टी0सी0।। दिनांक 25/11/2021
TS Amount (lakhs) : 147.88 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
73.94
Resanction Cost :
73.94
Tentative Cost :
73.94
Exp. Upto Last Fy :
19.90
For CFY 2025-2026
Remaining :
54.04
Demand :
50.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
19.90
Construction Started
Sanction on : 3 years 4 months ago
25 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 01-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: