Work Profile Report [71W717]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0-3260/।।। (2)/ 21- 41 (एम0एल0ए0) /2017 दिनांक 2/9/2021
TS Amount (lakhs) : 163.19 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
163.19
Resanction Cost :
163.19
Tentative Cost :
163.19
Exp. Upto Last Fy :
145.17
For CFY 2025-2026
Remaining :
18.02
Demand :
18.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
145.17
Construction Started
Sanction on : 3 years 7 months ago
02 Sep 2021
Physical Progress:
At start of FY 2025-2026 :
85 %
Up to Date :
85 %
Tentative Completion date on : 1 year 10 months ago
20 Jun 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 11-Apr-2025
Assets :
Work not linked with IM