Work Profile Report [71W12]

देवीखाल(भदालीखाल) सें जुंकरसैण-फतेहपुर मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0-2935/।।।-(2)/ 06-59(प्रा0आ0)/06 दि0 22/11/2006

TS Amount (lakhs) : 172.5 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

172.50

Resanction Cost :

172.50

Tentative Cost :

172.50

Exp. Upto Last Fy :

132.77

For CFY 2025-2026

Remaining :

39.73

Demand :

39.73

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

132.77

Construction Started

Sanction on : 18 years 5 months ago

22 Nov 2006

Physical Progress:

At start of FY 2025-2026 :

35 %

Up to Date :

35 %

Tentative Completion date on : 10 months 4 weeks from now

24 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
0
0
-

Remark

view all

3.50 कि0मी0 में कार्य पूर्ण। शेष भाग में वन भूमि पड़ती है, जिसका वन भूमि प्रस्ताव आपत्तियों में प्राप्त। -- as on 04-Nov-2024

Rating : 85

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: