Work Profile Report [71W12]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-2935/।।।-(2)/ 06-59(प्रा0आ0)/06 दि0 22/11/2006
TS Amount (lakhs) : 172.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
172.50
Resanction Cost :
172.50
Tentative Cost :
172.50
Exp. Upto Last Fy :
132.77
For CFY 2025-2026
Remaining :
39.73
Demand :
39.73
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
132.77
Construction Started
Sanction on : 18 years 5 months ago
22 Nov 2006
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
35 %
Tentative Completion date on : 10 months 4 weeks from now
24 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.50 कि0मी0 में कार्य पूर्ण। शेष भाग में वन भूमि पड़ती है, जिसका वन भूमि प्रस्ताव आपत्तियों में प्राप्त। -- as on 04-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: