Work Profile Report [70W601]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 66794, दि0 20-12-2024
TS Amount (lakhs) : 75.69 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
75.69
Resanction Cost :
75.69
Tentative Cost :
75.69
Exp. Upto Last Fy :
22.95
For CFY 2025-2026
Remaining :
52.74
Demand :
50.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
22.95
Construction Started
Sanction on : 4 months 4 days ago
20 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
45 %
Tentative Completion date on : 6 months 1 week from now
06 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य प्रगति पर। -- as on 09-Apr-2025