Administrative Approval Detail : शासनादेश सं0 7349/।।।(2)/2024-01(प्रा0आ0)/2023, दिनांक 06.11.2024
TS Amount (lakhs) : 497.28 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
497.28
Resanction Cost :
497.28
Tentative Cost :
497.28
Exp. Upto Last Fy :
400.00
For CFY 2025-2026
Remaining :
97.28
Demand :
97.28
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
400.00
Work completed
Sanction on : 5 months 2 weeks ago
06 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 month 6 days from now
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 29-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: