Work Profile Report [70W529]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 41863, दि0 15.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
236.18
Resanction Cost :
236.18
Tentative Cost :
236.18
Exp. Upto Last Fy :
178.24
For CFY 2025-2026
Remaining :
57.94
Demand :
45.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
178.24
Construction Started
Sanction on : 1 year 1 month ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 2 weeks 6 days from now
15 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 29-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: