Work Profile Report [70W521]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-37977, दिनांक 01-03-2024
TS Amount (lakhs) : 70.72 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
70.72
Resanction Cost :
70.72
Tentative Cost :
70.72
Exp. Upto Last Fy :
0.21
For CFY 2025-2026
Remaining :
70.51
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.21
Construction Started
Sanction on : 1 year 1 month ago
01 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य प्रगति पर। -- as on 31-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand