Administrative Approval Detail : शासन की ई0 पत्रावली सं0 48114, दि0 25.01.2024
TS Amount (lakhs) : 6.55 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.55
Resanction Cost :
6.55
Tentative Cost :
6.55
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
6.46
Demand :
6.46
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.09
Survey work done
Sanction on : 1 year 2 months ago
25 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
45 %
Tentative Completion date on : 6 months 6 days from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0पी0आर0 गठित कर डिजाइन सैल, देहरादून को प्रेषित। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: