Work Profile Report [70W478]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 30.10.2023
TS Amount (lakhs) : 4.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy :
3.28
For CFY 2025-2026
Remaining :
1.22
Demand :
1.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.28
Survey work done
Sanction on : 1 year 5 months ago
30 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
35 %
Tentative Completion date on : 8 months 3 days from now
28 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण कार्य पूर्ण। संरेखण गठन की कार्यवाही प्रगति पर। -- as on 11-Feb-2025
Assets :
Work not linked with IM