Work Profile Report [70W417]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 02.05.2023
TS Amount (lakhs) : 128.06 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
128.06
Resanction Cost :
128.06
Tentative Cost :
128.06
Exp. Upto Last Fy :
124.28
For CFY 2025-2026
Remaining :
3.78
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
124.28
Work completed
Sanction on : 2 years 8 hours ago
02 May 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 month ago
31 Mar 2024
Actual Completion Date : 1 year 2 months ago
01 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 31-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: