Work Profile Report [70W3]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 1372/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0 ।।। दिनांक 21.05.2021
TS Amount (lakhs) : 79.79 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
79.79
Resanction Cost :
79.79
Tentative Cost :
79.79
Exp. Upto Last Fy :
46.42
For CFY 2025-2026
Remaining :
33.37
Demand :
33.37
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
46.42
Construction Started
Sanction on : 3 years 11 months ago
21 May 2021
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य प्रगति पर। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand