Work Profile Report [70W229]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5937/(।।)/ैै।।।(2) 18-39 (एम0एल0ए0)/2017 टी0सी0 दि0 07.12.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
23.25
Resanction Cost :
23.25
Tentative Cost :
23.25
Exp. Upto Last Fy :
21.67
For CFY 2025-2026
Remaining :
1.58
Demand :
1.58
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
21.67
Construction Started
Sanction on : 6 years 4 months ago
07 Dec 2018
Physical Progress:
At start of FY 2025-2026 :
85 %
Up to Date :
85 %
Tentative Completion date on : 7 months 5 days from now
30 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
90 प्रतिशत मुआवजा भुगतान किया जा चुका है। काश्तकारों के न आने के कारण भुगतान अवशेष। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: