Work Profile Report [70W213]

सारी-डेबडाली-कालौजल मोटर मार्ग का विस्तारीकरण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : fजलाfधकारी/मुख्य fवकास अfधकारी के पत्रांक 859 /वा0fज0यो0/2018-19 fद0 14.08.2018

TS Amount (lakhs) : 19.44 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

20.00

Resanction Cost :

20.00

Tentative Cost :

20.00

Exp. Upto Last Fy :

5.80

For CFY 2025-2026

Remaining :

14.20

Demand :

14.20

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

5.80

Work completed

Sanction on : 6 years 8 months ago

14 Aug 2018

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 month 6 days from now

31 May 2025

Actual Completion Date : 1 year 3 weeks ago

28 Mar 2024

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

कार्य पूर्ण। -- as on 31-Jan-2025

Rating : 103

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand