Work Profile Report [70W174]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 508/।।।(2)/18-39(एम0एल0ए0)/2017 दि0 09.02.2018
TS Amount (lakhs) : 21.63 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
21.63
Resanction Cost :
21.63
Tentative Cost :
21.63
Exp. Upto Last Fy :
8.53
For CFY 2025-2026
Remaining :
13.10
Demand :
13.10
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
8.53
Survey work done
Sanction on : 7 years 2 months ago
09 Feb 2018
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
40 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
संरेखण प्रेषित। मुआवजा भुगतान अवशेष है। -- as on 29-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: