Work Profile Report [70W145]

ग्राम च्वारा में किमी0 1 से मोटर मार्ग का विस्तारीकरण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : fजलाfधकारी पौड़ी के पत्रांक 1058/fज0यो0/ लो0fन0fव0/2016-17 fद0 31.08.2016

TS Amount (lakhs) : 24.81 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

24.81

Resanction Cost :

24.81

Tentative Cost :

24.81

Exp. Upto Last Fy :

17.38

For CFY 2025-2026

Remaining :

7.43

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

17.38

Work completed

Sanction on : 8 years 7 months ago

31 Aug 2016

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 3 months 6 days from now

31 Jul 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
0.5
0.5
0.5
-

Remark

view all

कार्य पूर्ण। -- as on 29-Mar-2025

Rating : 106

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: