Work Profile Report [70W123]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1418/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0-1 दिनांक 31.05.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
28.02
Resanction Cost :
28.02
Tentative Cost :
28.02
Exp. Upto Last Fy :
3.72
For CFY 2025-2026
Remaining :
24.30
Demand :
24.30
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.72
Construction Started
Sanction on : 3 years 10 months ago
31 May 2021
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
15 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण स्टेज-। की स्वीकृति प्राप्त। मुआवजा गठन की कार्यवाही की जानी है। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: