Work Profile Report [6W966]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्‘शासनादेश सं0-7779/।।।(2)/2024-01(प्रा0आ0)/2023 ई0 फाइल सं0 56385 दिनांक 27.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1249.85
Resanction Cost :
1249.85
Tentative Cost :
1249.85
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
1,249.85
Demand :
1,000.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 3 months 4 weeks ago
27 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 4 months 4 weeks from now
24 Sep 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबंध गठित। कार्य प्रगति पर है। -- as on 29-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand