Work Profile Report [6W954]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य विकास अधिकारी बागेश्वर के पत्र सं0 467/जि0यो0/2024-25 दिनांक 24.06.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.00
Resanction Cost :
50.00
Tentative Cost :
50.00
Exp. Upto Last Fy :
31.19
For CFY 2025-2026
Remaining :
18.81
Demand :
16.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
31.19
Construction Started
Sanction on : 10 months 16 hours ago
24 Jun 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 1 month 6 days from now
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवारों का कार्य पूर्ण। सोलिंग कार्य प्रगति पर। -- as on 21-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: