Work Profile Report [6W910]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य विकास अधिकारी बागेश्वर के पत्र सं0 467/जि0यो0/2024-25 दिनांक 24.06.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy :
2.81
For CFY 2025-2026
Remaining :
7.19
Demand :
7.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.81
Construction Started
Sanction on : 10 months 16 hours ago
24 Jun 2024
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
70 %
Tentative Completion date on : 4 months 5 days from now
30 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 20-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand