Administrative Approval Detail : ई फाइत संख्या 51057 दिनांक 07.08.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
122.22
Resanction Cost :
122.22
Tentative Cost :
122.22
Exp. Upto Last Fy :
57.85
For CFY 2025-2026
Remaining :
64.37
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
57.85
Construction Started
Sanction on : 1 year 8 months ago
07 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 1 month 2 weeks from now
15 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3 किमी0 पहाड कटान का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 21-Feb-2025