Work Profile Report [6W465]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी बागेश्वर के पत्रांक सं0 405/fज0यो0/2015-16 fदनांक 29 मई, 2015
TS Amount (lakhs) : 100 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
100.00
Resanction Cost :
100.00
Tentative Cost :
100.00
Exp. Upto Last Fy :
89.20
For CFY 2025-2026
Remaining :
10.80
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
89.20
Work completed
Sanction on : 9 years 10 months ago
29 May 2015
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 4 months ago
29 Nov 2022
Actual Completion Date : 2 years 4 months ago
29 Nov 2022
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 29-Nov-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI: