Work Profile Report [69W376]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई पत्रावली संख्या - 48456 दिनांक 07 मार्च 2024।
TS Amount (lakhs) : 261.39 Lacs
Budget Financial Head : अनुरक्षण ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
261.39
Resanction Cost :
261.39
Tentative Cost :
261.39
Exp. Upto Last Fy :
125.06
For CFY 2025-2026
Remaining :
136.33
Demand :
136.33
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
125.06
Construction Started
Sanction on : 1 year 1 month ago
07 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
30 %
Up to Date :
30 %
Tentative Completion date on : 1 month 6 days from now
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में है। -- as on 02-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: