Work Profile Report [69W335]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-पत्रावली सं0 36087 लोक निर्माण अनुभाग-2 दि0 30.06.2023
TS Amount (lakhs) : 79.78 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
79.78
Resanction Cost :
79.78
Tentative Cost :
79.78
Exp. Upto Last Fy :
78.52
For CFY 2025-2026
Remaining :
1.26
Demand :
1.26
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
78.52
Work completed
Sanction on : 1 year 9 months ago
30 Jun 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 25-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: