Administrative Approval Detail : ाा0सं0 2531/111 -2/06-80 (प्रा0आ0)/05 दिनांक 30.08.06

TS Amount (lakhs) : 1433.39 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

1579.80

Resanction Cost :

1579.80

Tentative Cost :

1201.84

Saving

377.96

Exp. Upto Last Fy :

1,189.84

For CFY 2025-2026

Remaining :

389.96

Demand :

12.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1,189.84

Construction Started

Sanction on : 18 years 7 months ago

30 Aug 2006

Physical Progress:

At start of FY 2025-2026 :

95 %

Up to Date :

95 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
21
21
21
-
Bridge
3 (362m)
3 (362m)
3 (362m)
-

Remark

view all

Overall Saving 377.96 has been recorded as expected cost of work reduced from 1579.8 to 1201.84 . -- as on 08-Apr-2025

Rating : 95

No Forest Case in The Work

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: