Work Profile Report [69W289]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ाा0सं0 2531/111 -2/06-80 (प्रा0आ0)/05 दिनांक 30.08.06
TS Amount (lakhs) : 1433.39 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1579.80
Resanction Cost :
1579.80
Tentative Cost :
1201.84
Saving
377.96
Exp. Upto Last Fy :
1,189.84
For CFY 2025-2026
Remaining :
389.96
Demand :
12.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,189.84
Construction Started
Sanction on : 18 years 7 months ago
30 Aug 2006
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 377.96 has been recorded as expected cost of work reduced from 1579.8 to 1201.84 . -- as on 08-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: