Work Profile Report [68W350]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली संख्या 66794 लोक निर्माण अनुभाग-2 देहरादून दिनांक 12/03/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
222.89
Resanction Cost :
222.89
Tentative Cost :
222.89
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
222.79
Demand :
190.00
Allotment :
69.32
Exp in CFY :
69.32
Total Up to Date Exp :
69.42
Construction Started
Sanction on : 5 months 4 weeks ago
12 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
15 %
Tentative Completion date on : 6 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सोलिंग का कार्य प्रगति पर है (पूर्व में त्रृटिवश टाॅप कोट लिखा गया था ) -- as on 15-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: