Work Profile Report [68W29]

जनपद पौडी गढवाल के विकासखण्ड पोखडा में तलगत मोटर मार्ग निर्माण कार्य। ।।।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : ंं शासनादेश सं0 1153/।।।(2)/16-56 (प्रा0आ0)/2015 टी0सी0 दिनंाक 29.02.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

44.29

Resanction Cost :

44.29

Tentative Cost :

44.29

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

44.29

Demand :

15.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Unstarted Work

Sanction on : 9 years 1 month ago

29 Feb 2016

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 3 weeks 3 days ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
1
1
1
-

Remark

view all

प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी के द्वारा प्रस्ताव पर पुनः आपत्ति लगाई गई है जिसका निराकरण इस कार्यालय के पत्र संख्या 629/2भू0अ0 दिनांक 03.06.2024 के द्वारा ऑनलाइन/ऑफलाइन कर प्रभागीय वनाधिकारी गढ़वाल वनप्रभाग पौड़ी को प्रेषित कर दिया गया है। वर्तमान में प्रस्ताव आर0ओ0 स्तर पर लम्बित है। -- as on 09-Sep-2024

Rating : 0

No Forest Case in The Work

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: