Administrative Approval Detail : 6008 (1) /III (2) / 21-37 (MLA) 2017 TCII
TS Amount (lakhs) : 142.6 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
142.60
Resanction Cost :
142.60
Tentative Cost :
142.60
Exp. Upto Last Fy :
128.93
For CFY 2025-2026
Remaining :
13.67
Demand :
13.67
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
128.93
In Maintenance After Completion
Sanction on : 3 years 4 months ago
11 Dec 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 4 months ago
01 Dec 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 27-Mar-2024
Assets :
Work not linked with IM