Work Profile Report [68W187]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6008 (1) /III (2) / 21-37 (MLA) 2017 TCII
TS Amount (lakhs) : 261.88 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
261.88
Resanction Cost :
261.88
Tentative Cost :
261.88
Exp. Upto Last Fy :
237.85
For CFY 2025-2026
Remaining :
24.03
Demand :
24.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
237.85
Work completed
Sanction on : 3 years 4 months ago
11 Dec 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 5 days ago
19 Apr 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुरक्षण का कार्य प्रगति पर है। -- as on 24-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand