Work Profile Report [68W167]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2344(1) /III (2) / 21-39 (MLA) / 2017 T.C-1 Dated 30 july 2021
TS Amount (lakhs) : 102.84 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
102.84
Resanction Cost :
102.84
Tentative Cost :
102.84
Exp. Upto Last Fy :
99.55
For CFY 2025-2026
Remaining :
3.29
Demand :
3.29
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
99.55
In Maintenance After Completion
Sanction on : 3 years 8 months ago
30 Jul 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुरक्षण का कार्य किया जा रहा है। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: