Work Profile Report [67W664]

घण्डियाल पाली मोटर मार्ग से डांगी तक सम्पर्क मार्ग का निर्माण कर्य। (द्वितीय चरण स्टेज-।)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 6029/।।।(2)/21-37(एम0एल0ए0)2017 दि0 14.12.2021

TS Amount (lakhs) : 56.61 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

80.57

Resanction Cost :

80.57

Tentative Cost :

80.57

Exp. Upto Last Fy :

19.78

For CFY 2025-2026

Remaining :

60.79

Demand :

20.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

19.78

Construction Started

Sanction on : 3 years 4 months ago

14 Dec 2021

Physical Progress:

At start of FY 2025-2026 :

70 %

Up to Date :

70 %

Tentative Completion date on : 11 months 6 days from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
2.000
1
0.000
0.000
Jobs
3
3
0
3
0
0

Remark

view all

2.00 कि0मी0 कार्य पूर्ण। 1 कि0मी0 में समरेखण विवाद। उक्त मोटर मार्ग पर डांगी गांव संयोजित हो चुका है। -- as on 05-Mar-2024

Rating : 115

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: