Work Profile Report [67W625]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1389/।।।(2)/21-37(एम0एल0ए0)/2017टी0सी0-2 दि0 21.05.2021
TS Amount (lakhs) : 49.32 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
49.32
Resanction Cost :
49.32
Tentative Cost :
49.32
Exp. Upto Last Fy :
46.28
For CFY 2025-2026
Remaining :
3.04
Demand :
2.32
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
46.28
Work completed
Sanction on : 3 years 11 months ago
21 May 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 04-Jun-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand