Work Profile Report [67W562]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 512/।।।(2)/20-37(एम0एल0ए0)/2017टी0सी0-1 दि0 03.02.2020
TS Amount (lakhs) : 174.37 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
174.37
Resanction Cost :
174.37
Tentative Cost :
174.37
Exp. Upto Last Fy :
169.00
For CFY 2025-2026
Remaining :
5.37
Demand :
5.37
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
169.00
Work completed
Sanction on : 5 years 2 months ago
03 Feb 2020
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: