Work Profile Report [67W525]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 8111/।।।(2)/18-37(एम0एल0ए0)/2017 दि0 28.12.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
153.65
Resanction Cost :
153.65
Tentative Cost :
153.65
Exp. Upto Last Fy :
28.19
For CFY 2025-2026
Remaining :
125.46
Demand :
30.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
28.19
Phase1 DPR Submitted
Sanction on : 6 years 3 months ago
28 Dec 2018
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
20 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण का कार्य पूर्ण। अवशेष प्रतिकर भुगतान की कार्यवाही गतिमान है। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: