Work Profile Report [62W10]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/Annual Plan2022-23/Barkot/landslide (C.No. 219340) dated 20.02.2023
TS Amount (lakhs) : 5303.29 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
5303.00
Resanction Cost :
5303.00
Tentative Cost :
5303.00
Exp. Upto Last Fy :
2,118.00
For CFY 2025-2026
Remaining :
3,185.00
Demand :
558.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2,118.00
Construction Started
Sanction on : 2 years 2 months ago
20 Feb 2023
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 2 months 3 days ago
21 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
date of start -22.09.2023
physical progress- 95%
-- as on 22-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: