Work Profile Report [59W2329]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-58709/29 दि0 11.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
59.38
Resanction Cost :
59.38
Tentative Cost :
59.38
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
59.38
Demand :
59.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
in Tendering Stage
Sanction on : 1 month 1 week ago
11 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
निविदा आमंत्रण में है। -- as on 12-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: