Work Profile Report [59W2304]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435/30 दि0 02.12.2024
TS Amount (lakhs) : 17.92 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
17.92
Resanction Cost :
17.92
Tentative Cost :
17.92
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
17.92
Demand :
17.90
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 4 months 3 weeks ago
02 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 3 weeks 4 days ago
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
400 मीटर लम्बाई में कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 26-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand