Work Profile Report [59W2133]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435 दिनांक 31.07.2023
TS Amount (lakhs) : 44.95 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
44.95
Resanction Cost :
44.95
Tentative Cost :
44.95
Exp. Upto Last Fy :
14.36
For CFY 2025-2026
Remaining :
30.59
Demand :
30.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
14.36
Work completed
Sanction on : 1 year 8 months ago
31 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 01/2025 -- as on 01-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand