Work Profile Report [59W2131]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435 दिनांक 31.07.2023
TS Amount (lakhs) : 44.07 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
44.07
Resanction Cost :
44.07
Tentative Cost :
44.07
Exp. Upto Last Fy :
17.70
For CFY 2025-2026
Remaining :
26.37
Demand :
26.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
17.70
Construction Started
Sanction on : 1 year 7 months ago
31 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
64 %
Up to Date :
64 %
Tentative Completion date on : 6 months 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.700 किमी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 01-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: