Work Profile Report [56W626]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 1943/।।।(2)/21-30(प्रा0आ0)2017टी0सी0-2 दिनांक 02.07.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
59.20
Resanction Cost :
59.20
Tentative Cost :
34.62
Saving
24.58
Exp. Upto Last Fy :
32.62
For CFY 2025-2026
Remaining :
26.58
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
32.62
Phase1 DPR Submitted
Sanction on : 3 years 9 months ago
02 Jul 2021
Physical Progress:
At start of FY 2025-2026 :
56 %
Up to Date :
56 %
Tentative Completion date on : 1 year 8 months from now
31 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 24.58 has been recorded as expected cost of work reduced from 59.2 to 34.62 . -- as on 16-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: