Work Profile Report [56W614]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0-616/।।।(2)/21-01(प्रा0आ0)/2020 दि0 19.03.2021
TS Amount (lakhs) : 228.37 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
228.37
Resanction Cost :
245.50
Tentative Cost :
245.50
Exp. Upto Last Fy :
234.57
For CFY 2025-2026
Remaining :
10.93
Demand :
1.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
234.57
In Maintenance After Completion
Sanction on : 4 years 1 month ago
19 Mar 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 3 weeks ago
31 Mar 2022
Actual Completion Date : 2 years 5 months ago
01 Nov 2022
Physical Linear Components
Remark
माह नवम्बर 2023 में भौतिक रूप से से पांच वर्षिय अनुरक्षण कार्य को छोडते हुए कार्य पूर्ण। कार्य अनुरक्षण अवधि में। -- as on 06-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: